Shoreline Substantial Development Permit
Required for substantial development within shoreline jurisdiction (200 feet of the ordinary high water mark) on marine, lake, and river shorelines in Washington.
Local City/County (Dept. of Ecology oversight) Puget Sound 90–180 days
Standard Operating Procedure
- 1Step 1
Determine whether your project meets the substantial development threshold by area, value, or use.
- 2Step 2
Submit a JARPA and shoreline application to your local government's shoreline administrator.
- 3Step 3
Local review includes consistency with the Shoreline Master Program and a public hearing before the hearing examiner.
- 4Step 4
The Dept. of Ecology reviews and either approves, approves with conditions, or denies the local decision.
- 5Step 5
Appeals, if any, are heard by the Shorelines Hearings Board within 30 days of Ecology's decision.