Water & Shoreline
Hydraulic Project Approval
Required for any work that uses, diverts, obstructs, or changes the natural flow or bed of state waters to protect fish life.
WA Dept. of Fish & Wildlife Coastal 45–90 days
Standard Operating Procedure
- 1Step 1
Submit the HPA application with project drawings to WDFW.
- 2Step 2
A habitat biologist reviews the application and may conduct a site visit.
- 3Step 3
WDFW determines mitigation conditions and timing restrictions to protect fish life.
- 4Step 4
The HPA is issued with site-specific conditions; work must follow the approved plan.
- 5Step 5
Submit a completion report once in-water work is finished to close out the approval.
Ready to begin?
Start your application and track its progress from your resident dashboard.