Conditional Use Permit

Allows a use that is not permitted outright in a zoning district but is conditionally allowed subject to review and specific conditions to protect neighboring properties.

Local County/City Planning Dept. Statewide 8–12 weeks

Standard Operating Procedure

  1. 1
    Step 1

    Pre-application meeting with local planning staff to confirm the use is eligible for conditional review.

  2. 2
    Step 2

    Submit the application with site plan, narrative, and notification materials.

  3. 3
    Step 3

    Staff reviews for completeness and schedules a public hearing before the hearing examiner or planning commission.

  4. 4
    Step 4

    The hearing body issues a decision with conditions designed to mitigate impacts on the neighborhood.

  5. 5
    Step 5

    Decisions can be appealed to the local Board of Adjustment or superior court within the local appeal period.